- Oct 30th - On Wed Oct 28th, Niels Michaelson of IJAF/CUO and Colin
Aspin visited Prototech AS in Bergen, NO to inspect the re-make of the
NOTCam vaccuum vessel and define acceptance tests for it. A
report
on the result of the visit to Prototech is given here. The vessel has
been re-made well and is close to meeting all vacuum requirements. After
an overnight pumping we acheived a vacuum of 1.8x10^-6 mbars!
- Unfortunately, NOTCam work has encountered some delays to the
planned schedule. NOTCam telescope commissioning was planned for Sept
98 but due to problems with the construction of the large custom
vacuum vessel, this has been delayed until Feb/Mar 99. Upon Lab
testing of the vacuum vessel in Copenhagen, it was discovered to have
several major problems which h required a re-make of much of the
vessel itself. The re-make has now been completed and Colin Aspin and
Niels Michaelson (of CUO) will visit Prototech AS in Bergen, NO in late
Oct to (hopefully) accept the new vessel. It has so far passed its vacuum
and leak testing at Prototech, fingers crossed for a successful acceptance
test!
- During integration work at CUO in June we successfully tested out the
cold table assemblies incl. all (8) motorized units. Bearings on cold
motors were changed and cold tested and almost all internal wiring from
motorized unit to the electrical vacuum connectors was completed. Test
cables for the motorized units were made and tested also. Progress was
made on the array electronics and the motor control electronics were
tested and found to work extremely well. Much work remains however, mostly
related to the vacuum vessel. This work will continue at CUO once the
vacuum vessel is delivered, hopefully in early Nov 98. It is anticipated
that 6-8 weeks work remains at CUO before delivery of the instrument to
La Palma for lab testing there and eventual telescope testing.
- The design for the first generation grisms for NOTCam is almost complete
and soon the drawings will be sent to Milton-Roy in the U.S.A. for
quotations.
- NOTCam has been advertised as available for 1 night runs performed
by NOT staff for the next semester (Nov 98 deadline, semester 99A observing).
We are optimistic that this initial observing phase will go ahead as planned.
| |