Work has continued with the installation of the automated side-ports. All the control boxes for the motors are now mounted and the communication wiring is almost complete. Some of the cable assemblies between the control boxes and the motors have been made. Power cabling to the boxes is still required. More rails have been mounted and almost all motors have been fitted to the side-ports.
Also here there has been some effect of the sickness of our technician, and we hope this to be finished soon after he returns to work.