Next: Instruments
Up: AiC Report to NOT
Previous: Down Time
Telescope pointing is now at 8.42'' rms. New automatic pointing model
data collection routine installed.
Combined M1, M2 reflectivity was measured at 60% in January 2001 down
from 66% in May 2000. Given the demands on technical time to be made
by commissioning of NOTCam and MOSCA, it was decided not to
realuminize M1 this summer, but we will explore the possibility of
realuminizing M2 as time allows. The reflectivity testing scheme is
under suspicion as indications of an uneven decay of M2 reflectivity
have not been borne out by strongly defocussed stellar images which
appear quite uniform. (PB)
Experiments using both the experimental adaptive optics system JOSE,
and raw data from the telescope load cells indicate the presence of a
vibration mode in the telescope system of around 12 Hz (probably
generated by the active optics system). A DSP-based digital filter
system will be implemented in the previously abandoned
load-cell/voice-coil mirror damping loop which will have a natural
frequency in this area. The visiting Swedish electronics student
Anders Magnusson will assist in this project. (GC)
See Appendix A for details.
Some progress has been made with the TCS upgrade project. Hardware
I/O tests are complete and coding has begun. Delays due to normal TCS
work now imply a project completion date of July 2003. (IS)
Project on hold due to lack of manpower.
The bursts of building crashes experienced in December 2000 and
February 2001 have been cause for concern. Their definitive cause
is still not known, but a number of possible causes have been addressed
already.
The December instances appeared to have been associated with noise in
the building/telescope position sensors, as a small modification to
the electrical grounding of these devices seemed to have a positive
effect. One curious characteristic of these crashes was that the
building and telescope remained in alignment throughout.
The February crashes occurred after the ( 200kg) thermal
insulation jacket was installed on FIES, and were more normal in that
building and telescope were found to be out of alignment after each
crash. Investigations showed that the hydrostatic bearing pads were
out of alignment, one seriously so. This was probably at least
contributory as the azimuth currents during slews were found to be
anomalously high indicating excessive friction. Discussions with
Torben Andersen and Niels Christian-Jessen helped us with diagnosis
and brought to light the original alignment jigs. Two of the three
the bearings were then realigned (the third is not perfect, but within
spec) and appear to be stable. Azimuth currents are now more normal.
Occasional unexplained building crashes (without telescope/building
misalignment) suggest that all is still not well and investigations
continue. The latest theory is that they are not building crashes at
all, but arise from anomolous responses from the safety system,
causing immediate power downs that appear like building crashes. As
it is, the crashes all seem to take place without the building and
telescope losing alignment as they would in the case of a true crash.
FIES, as a possible cause, was removed from its mount during this work
and remains off until we can be sure we have solved the problem and
may therefore monitor its effects more confidently. Expert advice has
been sought on the ability of the hydrostatic bearing to carry its
additional load and appears optimistic at the time of writing.
Next: Instruments
Up: AiC Report to NOT
Previous: Down Time
Tim Abbott, AiC
Wed Mar 21 12:56:05 GMT 2001
|